Object: Floating dock, Tallinn, Estonia.
Work: Renewal of dock steel constructions.
Customer: BLRT Grupp.
January 2003 |
|
Object: M/V “Theo”, Tallinn, Estonia.
Work: Stern rebuilding.
Customer: BLRT Grupp.
January 2003 |
|
Object: M/S “Casino Express”, work on voyage, Finland – Sweden.
Work: New ramp manufacture.
Customer: Longmarket Technology Ltd.
January-February 2003 |
|
Object: Air-cooled heat exchanger, Tallinn, Estonia.
Work: TIG welding of pipes.
Customer: Tallinna Masinatehas.
March 2003 |
|
Work: Steel structures manufacture.
Customer: Raumaster OY.
March 2003 |
|
Work: Chain conveyor and flue ducts manufacture.
Customer: Raumaster OY.
April 2003 |
|
Object: M/S “Monarch of the seas”, work on voyage, Fort Lauderdale – Los Angeles, USA.
Work: New deck manufacture, different welding works.
Customer: Longmarket Technology Ltd.
April – May 2003 |
|
Object: M/S “Radisson Diamond”, work on voyage, Fort Lauderdale, USA.
Work: Aluminum constructions repair.
Customer: Longmarket Technology Ltd.
May 2003 |
|
Object: M/V “Hadzy”, Tallinn, Estonia.
Work: Hull plates and frames renewal.
Customer: BLRT Grupp.
June 2003 |
|
Object: M/S “Monarch of the Seas”, work on voyage, Los-Angeles, USA.
Work: Welding works, repair of deck constructions.
Customer: Longmarket Technology Ltd.
July-August 2003 |
|
Work: Hatch covers manufacture.
Customer: Loksa Shipyard.
Julay-August 2003 |
|
Object: Baltic Shipyard, Tallinn, Estonia.
Work: Ship sections manufacture.
Customer: Marketex.
August 2003 |
|
Object: M/V “Sirri”, Tallinn, Estonia.
Work: Hull renewal.
Customer: BLRT Grupp.
August 2003 |
|
Object: M/S “Song of Flower”, work on voyage, Helsinki, Finland – Sankt-Petersburg, Russia.
Work: Tank top replacement.
Customer: Longmarket Technology Ltd.
August 2003 |
|
Object: M/S “Radisson Diamond”, work on voyage, Barcelona, Spain.
Work: Welding works, repair of deck constructions.
Customer: Longmarket Technology Ltd.
September 2003 |
|
Object: M/S “Nordlandia”, Tallinn, Estonia.
Work: Steel works.
Customer: LTH-Baas AS.
September 2003 |
|
Object: M/S “Alpina”, Loksa Shipyard.
Work: Renewal of bulkheads inside of ballast tanks.
Customer: LTH-Baas AS.
October 2003 |
|
Object: M/Y “Donia”, Tallinn, Estonia.
Work: New deckhouse and wheelhouse manufacture, aft part rebuilding.
Customer: Nordic Yacht Charter.
October – November 2003 |
|
Work: Caseages manufacture.
Customer: Fabec Elektroonika AS.
October-November 2003 |
|
Object: Boiler-house, Hedemora, Sweden.
Work: Erection of electrostatic precipitator ELPAC II.
Customer: Alstom.
November 2003 |
|
Object: Boiler-house, Kungsor, Sweden.
Work: Erection of electrostatic precipitator ELPAC II.
Customer: Alstom.
December 2003 |
|